In this blog you will be able to se construction of a large public decked area that we put up outside a
local sports center & spa.
There was just two of us working on the project and it took a three an a half weeks to construct from
our first day on site untill the finished item opened to the public.
Although there were only two of us doing the work we did need a little help with materiels deliveries
as the lorries couldnr get to the working area.
needed them. The hydraulic arm on the lorry was at full capacity when lifting the bundle, as can be
seen in the picture there was a couple of them.
Once we had some materieals the real work began.
we had already put the post holes in ready wich had been a trial of their own, however harder work was to come!
really show the amount of work that went into the decking.
i think our shortest day was about 9 hours and the longest 16 hours, we clocked nearly 500 hours from
start to finish.
Definatly a job i will always remember with fondness. i wish we had one every summer.
more description will be added over time of the work will be added later.
Thanks for looking!